Mike De Souza
“Enbridge says feds pushing ‘unrealistically fast’ approvals for pipeline”
Postmedia News
15 February 2012
Enbridge, the company behind a controversial pipeline proposal to link the Alberta oilsands with the British Columbia coast, has complained federal departments were asking it for too much information and pushing the approval process at an “unrealistically fast” pace, says newly released briefing material from Environment Canada.
The internal records contrast recent statements made by federal cabinet ministers and the Alberta-based energy company about delays in the review process for the proposed Northern Gateway Pipeline. If built, it would link the oilsands to the port of Kitimat so bitumen could be exported to Asia by tanker.
Paul Stanway, a spokesman for Enbridge, stressed in an interview Wednesday that the company raised these concerns early in the process, but that it was never proposing to slow down timelines for the project’s approval. While the company said that its discussions with the federal government were about its preference to delay detailed reports about its plans until after the project has received the green light from regulators, Environment Canada said Enbridge felt federal departments were “asking for more technical information and project design details” than the company was ready to provide at the time.
“The proponent has indicated that it is concerned that the Major Projects Management Office Project Agreement may be driving responsible authorities to issue project approvals within a time frame that is unrealistically fast, given the proponent’s commercial plans in that it prefers to proceed through the regulatory process without detailed route plans,” said Environment Canada in the briefing material that was released through access to information legislation. It was prepared for an October 29, 2010, meeting requested by Enbridge with the department’s deputy minister, Paul Boothe, and two officials from the Canadian Environmental Assessment Agency.
The Major Projects Management Office was launched by Prime Minister Stephen Harper’s government in 2007 to improve co-ordination and efficiencies in the regulatory review process of major resource projects.
Stanway noted that the review panel has asked for some of the additional engineering information that Enbridge has provided and continues to produce.
“If the suggestion is that we think we’d like to slow down the regulatory the process . . . I can tell you that’s absolutely not the case,” Stanway said.
He estimated Enbridge is spending about $300 million to prepare its case for regulatory approval, but that it does not immediately want spend millions of dollars on such additional work as detailed route plans until the project has approval.
He said this is a normal part of a regulatory review. “This is already a very expensive process,” he said.
NDP MP Nathan Cullen, who represents a British Columbia riding that would be affected by the proposed pipeline, said the revelations raise doubts about the federal government’s recent claims that Canada’s regulatory process is too slow. Instead, he said, it demonstrates that the project, which would go through the Great Bear Rainforest, is a complex one that needs to be studied carefully.
“These are complicated things and if you want to get them right you have to take your time and know what you’re talking about,” said Cullen, who is also a candidate in the NDP leadership race. “You can’t offer any comfort to Canadians if you don’t have your actual plans in place and ask this panel or the public to give their opinion and approval.”
The Environment Canada document also estimated Enbridge had offered about $8 million to local First Nations communities through 36 different agreements, as of August 2010, to help them research, while the Canadian Environmental Assessment Agency had distributed about $2.38 million in funding to 38 groups.
But the document also noted that there were over 100 aboriginal groups that might have an interest in the project along the entire length of the pipeline, and that the funding was “significantly lower than requested,” and could prevent some groups from fully participating in the project review.
Mike De Souza
“Enbridge says feds pushing ‘unrealistically fast’
approvals for pipeline”
Postmedia News
15 February 2012
Enbridge, the company behind a controversial pipeline proposal to link
the Alberta oilsands with the British Columbia coast, has complained
federal departments were asking it for too much information and pushing
the approval process at an “unrealistically fast” pace, says newly
released briefing material from Environment Canada.
The internal records contrast recent statements made by federal cabinet
ministers and the Alberta-based energy company about delays in the
review process for the proposed Northern Gateway Pipeline. If built, it
would link the oilsands to the port of Kitimat so bitumen could be
exported to Asia by tanker.
Paul Stanway, a spokesman for Enbridge, stressed in an interview
Wednesday that the company raised these concerns early in the process,
but that it was never proposing to slow down timelines for the project’s
approval. While the company said that its discussions with the federal
government were about its preference to delay detailed reports about its
plans until after the project has received the green light from
regulators, Environment Canada said Enbridge felt federal departments
were “asking for more technical information and project design details”
than the company was ready to provide at the time.
“The proponent has indicated that it is concerned that the Major
Projects Management Office Project Agreement may be driving responsible
authorities to issue project approvals within a time frame that is
unrealistically fast, given the proponent’s commercial plans in that it
prefers to proceed through the regulatory process without detailed route
plans,” said Environment Canada in the briefing material that was
released through access to information legislation. It was prepared for
an October 29, 2010, meeting requested by Enbridge with the department’s
deputy minister, Paul Boothe, and two officials from the Canadian
Environmental Assessment Agency.
The Major Projects Management Office was launched by Prime Minister
Stephen Harper’s government in 2007 to improve co-ordination and
efficiencies in the regulatory review process of major resource
projects.
Stanway noted that the review panel has asked for some of the additional
engineering information that Enbridge has provided and continues to
produce.
“If the suggestion is that we think we’d like to slow down the
regulatory the process . . . I can tell you that’s absolutely not the
case,” Stanway said.
He estimated Enbridge is spending about $300 million to prepare its case
for regulatory approval, but that it does not immediately want spend
millions of dollars on such additional work as detailed route plans
until the project has approval.
He said this is a normal part of a regulatory review. “This is already a
very expensive process,” he said.
NDP MP Nathan Cullen, who represents a British Columbia riding that
would be affected by the proposed pipeline, said the revelations raise
doubts about the federal government’s recent claims that Canada’s
regulatory process is too slow. Instead, he said, it demonstrates that
the project, which would go through the Great Bear Rainforest, is a
complex one that needs to be studied carefully.
“These are complicated things and if you want to get them right you have
to take your time and know what you’re talking about,” said Cullen, who
is also a candidate in the NDP leadership race. “You can’t offer any
comfort to Canadians if you don’t have your actual plans in place and
ask this panel or the public to give their opinion and approval.”
The Environment Canada document also estimated Enbridge had offered
about $8 million to local First Nations communities through 36 different
agreements, as of August 2010, to help them research, while the Canadian
Environmental Assessment Agency had distributed about $2.38 million in
funding to 38 groups.
But the document also noted that there were over 100 aboriginal groups
that might have an interest in the project along the entire length of
the pipeline, and that the funding was “significantly lower than
requested,” and could prevent some groups from fully participating in
the project review.
Mike De Souza
“Enbridge says feds pushing ‘unrealistically fast’
approvals for pipeline”
Postmedia News
15 February 2012
Enbridge, the company behind a controversial pipeline proposal to link
the Alberta oilsands with the British Columbia coast, has complained
federal departments were asking it for too much information and pushing
the approval process at an “unrealistically fast” pace, says newly
released briefing material from Environment Canada.
The internal records contrast recent statements made by federal cabinet
ministers and the Alberta-based energy company about delays in the
review process for the proposed Northern Gateway Pipeline. If built, it
would link the oilsands to the port of Kitimat so bitumen could be
exported to Asia by tanker.
Paul Stanway, a spokesman for Enbridge, stressed in an interview
Wednesday that the company raised these concerns early in the process,
but that it was never proposing to slow down timelines for the project’s
approval. While the company said that its discussions with the federal
government were about its preference to delay detailed reports about its
plans until after the project has received the green light from
regulators, Environment Canada said Enbridge felt federal departments
were “asking for more technical information and project design details”
than the company was ready to provide at the time.
“The proponent has indicated that it is concerned that the Major
Projects Management Office Project Agreement may be driving responsible
authorities to issue project approvals within a time frame that is
unrealistically fast, given the proponent’s commercial plans in that it
prefers to proceed through the regulatory process without detailed route
plans,” said Environment Canada in the briefing material that was
released through access to information legislation. It was prepared for
an October 29, 2010, meeting requested by Enbridge with the department’s
deputy minister, Paul Boothe, and two officials from the Canadian
Environmental Assessment Agency.
The Major Projects Management Office was launched by Prime Minister
Stephen Harper’s government in 2007 to improve co-ordination and
efficiencies in the regulatory review process of major resource
projects.
Stanway noted that the review panel has asked for some of the additional
engineering information that Enbridge has provided and continues to
produce.
“If the suggestion is that we think we’d like to slow down the
regulatory the process . . . I can tell you that’s absolutely not the
case,” Stanway said.
He estimated Enbridge is spending about $300 million to prepare its case
for regulatory approval, but that it does not immediately want spend
millions of dollars on such additional work as detailed route plans
until the project has approval.
He said this is a normal part of a regulatory review. “This is already a
very expensive process,” he said.
NDP MP Nathan Cullen, who represents a British Columbia riding that
would be affected by the proposed pipeline, said the revelations raise
doubts about the federal government’s recent claims that Canada’s
regulatory process is too slow. Instead, he said, it demonstrates that
the project, which would go through the Great Bear Rainforest, is a
complex one that needs to be studied carefully.
“These are complicated things and if you want to get them right you have
to take your time and know what you’re talking about,” said Cullen, who
is also a candidate in the NDP leadership race. “You can’t offer any
comfort to Canadians if you don’t have your actual plans in place and
ask this panel or the public to give their opinion and approval.”
The Environment Canada document also estimated Enbridge had offered
about $8 million to local First Nations communities through 36 different
agreements, as of August 2010, to help them research, while the Canadian
Environmental Assessment Agency had distributed about $2.38 million in
funding to 38 groups.
But the document also noted that there were over 100 aboriginal groups
that might have an interest in the project along the entire length of
the pipeline, and that the funding was “significantly lower than
requested,” and could prevent some groups from fully participating in
the project review.
Mike De Souza
“Enbridge says feds pushing ‘unrealistically fast’
approvals for pipeline”
Postmedia News
15 February 2012
Enbridge, the company behind a controversial pipeline proposal to link
the Alberta oilsands with the British Columbia coast, has complained
federal departments were asking it for too much information and pushing
the approval process at an “unrealistically fast” pace, says newly
released briefing material from Environment Canada.
The internal records contrast recent statements made by federal cabinet
ministers and the Alberta-based energy company about delays in the
review process for the proposed Northern Gateway Pipeline. If built, it
would link the oilsands to the port of Kitimat so bitumen could be
exported to Asia by tanker.
Paul Stanway, a spokesman for Enbridge, stressed in an interview
Wednesday that the company raised these concerns early in the process,
but that it was never proposing to slow down timelines for the project’s
approval. While the company said that its discussions with the federal
government were about its preference to delay detailed reports about its
plans until after the project has received the green light from
regulators, Environment Canada said Enbridge felt federal departments
were “asking for more technical information and project design details”
than the company was ready to provide at the time.
“The proponent has indicated that it is concerned that the Major
Projects Management Office Project Agreement may be driving responsible
authorities to issue project approvals within a time frame that is
unrealistically fast, given the proponent’s commercial plans in that it
prefers to proceed through the regulatory process without detailed route
plans,” said Environment Canada in the briefing material that was
released through access to information legislation. It was prepared for
an October 29, 2010, meeting requested by Enbridge with the department’s
deputy minister, Paul Boothe, and two officials from the Canadian
Environmental Assessment Agency.
The Major Projects Management Office was launched by Prime Minister
Stephen Harper’s government in 2007 to improve co-ordination and
efficiencies in the regulatory review process of major resource
projects.
Stanway noted that the review panel has asked for some of the additional
engineering information that Enbridge has provided and continues to
produce.
“If the suggestion is that we think we’d like to slow down the
regulatory the process . . . I can tell you that’s absolutely not the
case,” Stanway said.
He estimated Enbridge is spending about $300 million to prepare its case
for regulatory approval, but that it does not immediately want spend
millions of dollars on such additional work as detailed route plans
until the project has approval.
He said this is a normal part of a regulatory review. “This is already a
very expensive process,” he said.
NDP MP Nathan Cullen, who represents a British Columbia riding that
would be affected by the proposed pipeline, said the revelations raise
doubts about the federal government’s recent claims that Canada’s
regulatory process is too slow. Instead, he said, it demonstrates that
the project, which would go through the Great Bear Rainforest, is a
complex one that needs to be studied carefully.
“These are complicated things and if you want to get them right you have
to take your time and know what you’re talking about,” said Cullen, who
is also a candidate in the NDP leadership race. “You can’t offer any
comfort to Canadians if you don’t have your actual plans in place and
ask this panel or the public to give their opinion and approval.”
The Environment Canada document also estimated Enbridge had offered
about $8 million to local First Nations communities through 36 different
agreements, as of August 2010, to help them research, while the Canadian
Environmental Assessment Agency had distributed about $2.38 million in
funding to 38 groups.
But the document also noted that there were over 100 aboriginal groups
that might have an interest in the project along the entire length of
the pipeline, and that the funding was “significantly lower than
requested,” and could prevent some groups from fully participating in
the project review.